What this is

How to change the end date of a campaign that's already live, for example to give it two more weeks. You do it on the campaign's Delivery page, then save and confirm.

Why it matters: a longer or shorter flight changes when your leads arrive. Weekly batches are added or removed to match, so check the pacing before you save.

Key takeaway: Open the campaign, go to the RFP tab, and open the Delivery page. Change the End date, check the batches and pacing, and click Save changes. Then click Yes, change the campaign. All publishers are notified, and they don't need to accept.

Watch the walkthrough on Loom


Words to know

  • Flight dates: your campaign's delivery window, from the start date to the end date.

  • Live campaign: a campaign that is currently running and delivering leads.

  • Batch: one weekly delivery of leads, used when the campaign delivers in Weekly batches.

  • Upload percentage: the share of your total lead volume delivered in one batch.

  • Pacing: how fast leads are delivered, either near-real-time or weekly.


Before you start

  • The campaign is Live or Scheduled. A Finished campaign can't be edited.

  • You know the new end date you want.

  • You know how the campaign delivers: Near real-time or Weekly batches. Only weekly batches have a pacing table to check.


Steps

Step 1: Open the campaign's RFP tab

  1. On the home screen, click the campaign you want to update.

  2. Click the RFP tab at the top.

You'll see the campaign brief, starting with Main information.

A live campaign with the RFP tab open and the pencil icon next to Main information

Watch this step on Loom (0:04)

Step 2: Go to the Delivery page

There are two ways to get there. Use either one.

From Main information:

  1. Click the pencil icon next to Main information.

  2. Under Flight dates, click Go to Delivery.

The Flight dates field is grayed out here. The page says: "Change the flight dates in the Delivery step to observe pacing."

The Main information edit page, with the grayed-out Flight dates field and the Go to Delivery link

Watch this on Loom (0:14)

From the Delivery section:

  1. On the RFP tab, scroll down to Delivery. It shows your batches and their upload dates.

  2. Click the pencil icon next to Delivery.

The Delivery section of the RFP tab, with the pencil icon and the batch table

Watch this on Loom (0:23)

Either way, you'll see the Delivery page, titled Let's dive into leads upload pacing.

Step 3: Change the end date

  1. Click End date.

  2. Pick the new end date in the calendar. For example, move it two weeks later.

The Delivery page with the Start date grayed out and the End date changed to a later date

Watch this step on Loom (0:36)

Note: On a live campaign, the Start date is grayed out. Delivery has already begun, so it can't move. On a Scheduled campaign, the same steps work, and you can change the Start date here too.

Step 4: Check the batches and pacing

This step is for campaigns that use Weekly batches. With Near real-time, there are no batches, so go to Step 5.

  1. Scroll down to Leads upload pacing.

  2. Check the new batches. A later end date adds batches, and the Upload percentage spreads evenly across them on its own.

  3. To change the split, type your own percentage for any batch before you save. To go back to an equal split, click Pace evenly.

  4. Check that Total shows 100%.

Watch this step on Loom (0:42)

Step 5: Save and confirm the change

  1. Click Save changes.

  2. Read the Summary of changes. It lists each field, the action (Updated or Added), and the old and new values.

  3. Click Yes, change the campaign. To go back and edit more, click Back.

The confirmation window with the Summary of changes, the Back button, and Yes, change the campaign

You'll see the message RFP is changed: "All publishers were notified of changes." The new flight dates show at the top of the campaign.

Publishers are only notified. They don't need to accept the new dates.

Watch this step on Loom (0:54)

Warning: Yes, change the campaign notifies all publishers on the campaign right away. Check the new end date and the batches before you confirm.


Rules and limits

If you want to…

What to know

Extend the end date

Follow the steps above. There's no latest end date. On weekly batches, new batches are added.

Shorten the end date

Fine if you need the campaign to end sooner. On a Weekly batches campaign, also switch to Near real-time, so publishers can speed up and still deliver in full.

Move the start date

Only while the campaign is Scheduled. Once it's Live, the start date is locked.

Add budget

A later end date doesn't add budget or lead goal. Adding budget is a separate step with the Add Budget action. See Adding Budget Mid-Flight.

A longer flight spreads your lead volume thinner each week. A shorter flight concentrates it.

Important: A big change to the end date significantly earlier can affect delivery. Move it only as far as you need, and check the new batches before you save.


Frequently asked questions

Can I change the start date of a live campaign?

  • No. Once a campaign is Live, the start date is locked. You can change it only while the campaign is Scheduled.

Do these steps work for a Scheduled campaign?

  • Yes. Use the same steps. On a Scheduled campaign, you can also change the Start date on the Delivery page.

How do I end my campaign sooner?

  • Pick an earlier End date on the Delivery page. If the campaign uses Weekly batches, also choose Near real-time under At what frequency would you like leads distributed? Publishers can then speed up and still deliver in full in less time.

Why can't I edit the dates in Main information?

  • The Flight dates field there is read-only. Click Go to Delivery and change the End date on the Delivery page.

Do publishers find out about the new dates?

  • Yes. When you click Yes, change the campaign, all publishers on the campaign are notified. They don't need to accept the new dates.

Does a later end date add budget or leads?

My save was held and I was asked to refresh. What happened?

  • Someone else changed the campaign after you opened it. Reload the campaign and make your change again, so you don't overwrite theirs.



Need help?

Tip: Contact support@audyence.com for campaign questions, platform feedback, or anything else.

Include the campaign name and the new end date you want in your email.